Hp Smart Update Manager User Manual Page 54

  • Download
  • Add to my manuals
  • Print
  • Page
    / 130
  • Table of contents
  • TROUBLESHOOTING
  • BOOKMARKS
  • Rated. / 5. Based on customer reviews
Page view 53
iLO inventory
1. From the iLO screen, highlight the iLO on which you want to take inventory.
2. Click ActionsInventory.
3. The iLO inventory procedure is the same as the Node Inventory procedure.
To inventory a node
1. From the Nodes screen, highlight the node and then click ActionsInventory.
2. Select a baseline, additional package, or both to apply to the node.
3. Click Inventory.
Deploying an iLO
1. From the iLO screen, highlight the iLO you want to deploy.
2. Click ActionsReview/Deploy.
3. The iLO Deploy procedure is the same as the Node Deploy procedure.
NOTE: When deploying updates through an ISO mounted virtually via iLO, HP SUM updates
the iLO firmware last, if necessary. After HP SUM deploys the iLO firmware, the iLO disconnects
from the ISO when it reboots to activate the firmware. Reconnect to the iLO and then remount the
ISO media. If HP SUM times out and displays an unable to connect error, refresh the browser. You
can then review the update status, and resume using HP SUM.
To deploy a node
1. From the Nodes screen, select a node to update, and then click ActionsReview/Deploy.
2. If you want to change installation options, click Installation Options and then select from the
following:
Downgrade: This allows you to downgrade all of the components in the node to an older
firmware version without clicking Force for each component in the baseline library list.
Rewrite: This allows you to rewrite the current firmware version to components in the node
without clicking Force for each component in the baseline library list.
3. If you want to downgrade or rewrite options to firmware or software only, click Force options
can be applied to, and then select from the following:
Firmware: This displays only firmware updates.
Software: This displays only software updates.
4. In the Associated Node Details field, select any nodes that you want to update.
5. In the Baseline Library field, select each component that you want to update. Use the Search
box to type in search terms for the components. For more information about an update, click
the version number. If you are deploying a Linux node, HP SUM displays only RPM updates
that are valid for your node.
NOTE: You can click Force to downgrade or rewrite a component that is available for
downgrade or rewrite. If you select Downgrade, Rewrite, or both in the Installation Options,
HP SUM does not display the Force button.
6. If you want to change when the node reboots after an update, click Reboot Options and do
the following:
a. In Reboot System After Installation, select No, If Needed, or Always.
b. In Reboot Delay (seconds), enter the number of seconds you want the node to wait before
beginning the reboot.
c. In the text box, enter a reboot message of up to 255 characters to display before the
node reboots.
54 Using the HP SUM GUI
Page view 53
1 2 ... 49 50 51 52 53 54 55 56 57 58 59 ... 129 130

Comments to this Manuals

No comments