Appendix A: HP site assessment 27
Appendix A: HP site assessment
HP POD 40c G2 site assessment checklist
During a survey of the readiness of a proposed customer site for the HP POD 40c G2, the site is inspected for
the following:
Accessibility of machinery for the transportation and installation of the HP POD 40c G2
Assessment of the suitability of the site infrastructure for installing the HP POD 40c G2 and for
supporting infrastructure preparation and serviceability requirements
HP responsibilities
Item Description Sign-off
1. Engagement plan
Develop an engagement plan with specific
requirements relating to the proposed installation site.
2. Site visits
Schedule site visits on mutually acceptable dates,
during normal HP business hours.
3. Test equipment
Document any test equipment used in the customer
report.
4. Installation site
review
Review and discuss the proposed installation site with
the customer. This initial review includes physical
examination of the proposed installation site and, at
the sole discretion of HP, can include physical
measurements of the area size and clearances.
5. Indoor/outdoor
installation
Identify whether the HP POD 40c G2 installation is
indoors or outdoors as this can affect the degree and
type of infrastructure required and the mounting needs.
6. Site pad
Inspect the proposed installation site to assess
compliance with the HP POD 40c G2 mounting
specifications. Ensure that the customer is fully aware
of the following requirements:
Proper support capabilities must exist. If the
customer intends to edge or point load on the utility
and cargo ends, there must be support in the center
to prevent deflection.
Upon installation, the POD structure must be
leveled to ≤ 0.5º, which can be checked at that
time with a surveyor’s transit.
Shimming is allowed around the perimeter of the
POD.
Place shims in increments across the length of the
HP POD 40c G2 to ensure that the HP POD 40c
G2 is level.
7. Materials and
construction
inspection
Visually inspect the materials and construction at the
proposed installation site to identify issues that can
impact the HP POD 40c G2 installation. Verify that the
area is adequate for truck delivery, staging, and crane
location.
Page view 26
1 2 ... 22 23 24 25 26 27 28 29 30 31 32 ... 40 41

Comments to this Manuals

No comments

Foremost AV equipment stands user manuals

The list of Foremost AV equipment stands products contains 12 user manuals for 12 models. All pdf user’s guides are available for download or viewing online.

Click on an alphabet below to scroll to the full list of models starting with that letter

Models Document Type
GAGM2432
Instruction Manual     Foremost GAGM2432 Instructions / Assembly, 4 pages
GAWW1924
Installation Guide   Foremost GAWW1924 Installation Guide, 4 pages
KOWA1934COMBO
Instruction Manual   Foremost KOWA1934COMBO Instructions / Assembly, 10 pages
KOWS0824
Instruction Manual   Foremost KOWS0824 Instructions / Assembly, 4 pages
NADGAT7222D
Instruction Manual     Foremost NADGAT7222D Instructions / Assembly, 5 pages
NADGL2474
Instruction Manual     Foremost NADGL2474 Instructions / Assembly, 4 pages
RACW1519
Instruction Manual   Foremost RACW1519 Instructions / Assembly, 5 pages
RACWH2015
Installation Guide     Foremost RACWH2015 Installation Guide, 5 pages
TENA3022
Instruction Manual     Foremost TENA3022 Instructions / Assembly, 4 pages
TENA5822D
Instruction Manual     Foremost TENA5822D Instructions / Assembly, 6 pages
TENW2528
Instruction Manual     Foremost TENW2528 Instructions / Assembly, 4 pages
WWMB1222
Instruction Manual     Foremost WWMB1222 Instructions / Assembly, 12 pages