Appendix B: Preparing for delivery 30
Item Description Initial
2
Verify that the chilled water supply temperature meets the minimum POD chilled water supply
temperature of 12°C (55°F).
3
Verify that a sufficient chilled water flow rate is available.
4
If necessary, verify that the customer-required chilled water return temperatures can be
attained.
Power Requirements
Item Description Initial
1
Verify that the short circuit analysis, arc flash, and circuit breaker coordination studies are
complete. Verify power work is completed according to the approved conduit routing
drawings that show the exact routes, plan view, sections, and elevations.
2
Verify that temporary site po
wer for installation and construction is planned and available, if
applicable.
3
Verify that adequate site power exists per the HP POD 20c requirements.
General
Item Description Initial
1
Verify the utility connection to the HP POD 20c and any required metering equipment.
2
Verify the third-party commissioning services that might be required by the owner.
3
Verify that the HP Project Team coordinates with other site construction activities.