Hardware options installation 76
7.
Install an expansion board into the PCI riser cage.
8. Install the optional secondary PCI riser cage.
9. If not already installed, install the secondary processor ("Processor and fan option" on page 42).
10. Install the access panel (on page 25).
11. Install the server into the rack ("Installing the server into the rack" on page 38).
12. Connect each power cord to the server.
13. Connect each power cord to the power source.
14. Power up the server (on page 23).
Hard drive cage option
A SAS expander card or an additional SAS controller option is required to support the hard drive cage
option.