HP Performance Optimized Datacenter 20c Site Preparation and Requirements Guide—North America Abstract This document provides site preparation guida
Site requirements 10 Side view clearances shown Top view for multiple POD installation minimum clearances shown Adequate space around the HP POD 2
Site requirements 11 Grounding requirements The HP POD 20c structure and internal components are all bonded together. A common grounding electrode c
Site requirements 12 Utilities Consider the proximity to required utilities, such as power, water, and network connections. While the required utili
Site requirements 13 Requirement Location Specification Humidifier drain Cold aisle side (1) 3.18 cm (1.25 in) drain line and 26.5 lpm (7 gpm) ma
Site requirements 14 Feature Specification Facility input temperature to the HP POD 20c 12º to 24ºC (55º to 75ºF) Max design pressure 1,034 kPa (1
Site requirements 15 These actions must be performed for all associated parts of the electrical power train. The majority of the details and factors
Supported facility connections 16 Supported facility connections Environmental control system The ECS developed for the HP water-cooled POD is a sta
Supported facility connections 17 End view shown Humidifier A dedicated water supply and approved drainage is required for the humidifier. For mor
Supported facility connections 18 HP POD 20c access control The HP POD 20c is equipped with standard key lock hardware for each personnel entry door
Supported facility connections 19 Front view shown You must make the connections between the facility and the HP POD 20c. For configuration and ins
© Copyright 2013 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. The only warranties
Environmental considerations 20 Environmental considerations Environmental risks • Avoid placing the HP POD 20c directly along a drainage path or i
Site plan requirements and actions 21 Site plan requirements and actions Completing a site assessment HP requires a detailed site assessment prior t
Site plan requirements and actions 22 • Ensure that the site safety and security programs are properly administered. • Interface directly with the
Site plan requirements and actions 23 • Assembly equipment locations Item Description 1 Crane 2 Reach 3 Truck 4 Area clear for scissors lift and
Site plan requirements and actions 24 Additional structures If a customer-provided vestibule or other structure is installed and connected to the HP
Appendix A: HP site assessment 25 Appendix A: HP site assessment HP POD 20c site assessment checklist During a survey of the readiness of a proposed
Appendix A: HP site assessment 26 Item Description Yes No N/A Initial 8. Clearances Inspect the proposed installation site to confirm clearance
Appendix A: HP site assessment 27 Item Description Yes No N/A Initial 15. Recommendations Following the HP installation site visit, analyze the
Appendix B: Preparing for delivery 28 Appendix B: Preparing for delivery Pre-delivery tasks Allow adequate time for planning, scheduling, obtaining
Appendix B: Preparing for delivery 29 Item Description Initial 10 Verify that the site location has clearances for the HP POD 20c installation, in
Contents 3 Contents Overview ...
Appendix B: Preparing for delivery 30 Item Description Initial 2 Verify that the chilled water supply temperature meets the minimum POD chilled wa
Appendix C: Regulatory compliance notices 31 Appendix C: Regulatory compliance notices HP POD 20c regulatory compliance The HP POD 20c complies with
Appendix C: Regulatory compliance notices 32 • The HP POD 20c is designed for stationary installation outdoors in a Pollution Degree 3 environment,
Glossary 33 Glossary AHJ authority having jurisdiction APJ Asia Pacific Japan BMS building management system door A hinged portion of an enclosur
Glossary 34 listed Equipment, materials, or services included in a list published by an organization that is acceptable to the authority having juri
Documentation feedback 35 Documentation feedback HP is committed to providing documentation that meets your needs. To help us improve the documentat
Index 36 A about this guide 5 areas prone to lightning or power surges 20 assembly 28 assembly area 22 C capacity limitations 7 clearance
Index 37 site planning considerations 22 site preparation 6 site preparation checklist 28 site requirements 8, 21 storage locations 23 sup
Contents 4 Project coordination ...
Overview 5 Overview About this document This document outlines the site and preparation requirements for a 6 m (20 ft) HP POD 20c as it is being rel
Overview 6 Feature Specification Class Class1 Ambient temperature 2°C to 54°C (35.6°F to 129.2°F) Relative humidity 0% to 100% humidity • As part
HP POD 20c capacities 7 HP POD 20c capacities HP POD 20c capacity limitations The capacity limitations for the HP POD 20c are separated into two cat
Site requirements 8 Site requirements Site pad The structural design of the HP POD 20c site pad must be based on the specific weight load of the com
Site requirements 9 End 1 view clearances shown Top view keep-out and door swing clearances shown (shaded areas indicate the required clearance)